What the NHVR actually requires in your maintenance records
The law does not hand you a form. It hands you a duty, and then, if you are accredited, a scheme that says what an auditor will want to see. There are two of those schemes running at once right now. Here is which one you are on, what each of them asks you to keep, and how long to keep it.
The short version
Every party in the chain has a primary duty under the Heavy Vehicle National Law to ensure the safety of their transport activities so far as is reasonably practicable. That includes how vehicles are maintained, and it applies whether or not you hold any accreditation. Reasonably practicable is a test you pass with evidence: you have to be able to show what you checked, what you found, what you did about it and when.
If you are accredited, the records are spelled out, but the two schemes spell them out differently. NHVAS has eight numbered Maintenance Management standards, listed below, and a quarterly compliance report. The HVA scheme, which replaced it on 1 August 2026, has no numbered maintenance standards and asks instead for records showing the work is being done as part of normal operations. What both want on the ground is identical: the daily check, the fault report, the repair record and the service schedule. Where they part company is retention. NHVAS says three years, and the 2026 HVA guideline names no period in years at all.
Which scheme are you on
Two accreditation schemes are running at once right now, and they ask for different things. If you hold NHVAS accreditation today then you are still on NHVAS, because it has not been switched off, and the eight numbered Maintenance Management standards further down are the ones your auditor will work through. If you came in after 1 August 2026, or you have already moved across, you are on the Heavy Vehicle Accreditation scheme, where there are no numbered maintenance standards at all and the requirements are written as outcomes instead. If you hold no accreditation then neither set binds you, but the primary duty does, and the records both schemes ask for are the plainest evidence that you are meeting it.
The practical test is your own paperwork: the label on the vehicle and the wording on your accreditation certificate will name the scheme you are in. That matters more than any transition date, because the NHVR has said operators have up to three years to move and, as far as we could find, has not published a final calendar date for it.
The daily checks, faults, repairs and service records this page describes are the ones AssetPass keeps as the work happens, under either scheme. Send your asset list and it comes back loaded.
Rather do it on a phone? Prestarts are free for up to 3 assets.
The duty everybody has
The primary duty provision of the HVNL puts the duty on ten kinds of party: the employer of a driver, the prime contractor, the operator, the scheduler, the consignor, the consignee, the packer, the loading manager, the loader and the unloader. The regulator's own advice on that duty says each of them must consider how heavy vehicle procurement and maintenance is undertaken and managed. A further provision adds a duty on executives to exercise due diligence to make sure the business complies.
In its regulatory advice on maintenance the NHVR describes what reasonable control measures look like: a systematic service schedule that follows the manufacturer's specifications, a daily checklist, a recording and reporting system for faults, defects and maintenance history, faults responded to and fixed in a timely manner, and grounding an unsafe vehicle until the defect is rectified. Read that list twice. It is the accreditation standards in everyday clothes, and it is what a reasonable operator is expected to be able to show whether they carry an accreditation label or not.
What changed on 1 August 2026
The amended Heavy Vehicle National Law commenced on 1 August 2026. With it came the Heavy Vehicle Accreditation scheme, and its own guideline says plainly that it replaces NHVAS. The accreditation types it offers are General Safety Accreditation, General Safety Accreditation with the Maintenance Assurance Program, and Alternative Compliance Accreditation for fatigue and for mass. Maintenance is the Assurance Program, not the Alternative Compliance stream, which is worth being precise about because the older tier lists in circulation put it in the wrong place. The Assurance Program carries on the exemption from the annual inspections that form part of registration, in New South Wales and Queensland.
The bigger change is in how an audit works. Instead of ticking through one module, the auditor assesses a whole of business safety management system, which the guideline builds from five connected components: leadership and commitment, risk management, safety systems, assurance, monitoring and improvement, and people. Maintenance is one thread running through that rather than a box of its own, which is why the maintenance wording is now about records showing the work happens rather than about criteria to satisfy.
If you hold NHVAS accreditation today, nothing stopped on the day. The NHVR's own implementation material puts it this way:
It's important to note that the existing National Heavy Vehicle Accreditation Scheme (NHVAS) will continue to operate during a transition period.HVNL implementation FAQs, NHVR
The same material gives the length of that period without giving it an end:
Operators currently accredited in the NHVAS will have up to three years to transition to the new scheme.HVNL implementation FAQs, NHVR
Three years from what is not spelled out, and we could find no published calendar date for the end of the transition anywhere on the NHVR site, so we are not going to quote you a deadline. The useful date is your own accreditation expiry. The daily records did not change either way: the daily check, the fault report, the repair record and the service schedule are what they were. What does not carry across is the three year retention number, as the section on how long to keep it explains below.
What the HVA scheme asks for
The NHVR's Heavy Vehicle Accreditation Scheme Operator Guideline 2026 states the change in one line:
The HVA scheme replaces the National Heavy Vehicle Accreditation Scheme (NHVAS).Heavy Vehicle Accreditation Scheme Operator Guideline 2026, NHVR
Where NHVAS set out eight numbered Maintenance Management standards, the HVA guideline sets out none. We searched it for the phrase Maintenance Management Standard 5 and could not find it, nor any numbered standard in that form. Maintenance instead sits inside the Maintenance Assurance Program, which runs under General Safety Accreditation, and the guideline organises it as four groups of controls: daily check controls, fault recording and reporting controls, fault repair controls, and maintenance schedules and methods controls.
The wording is outcomes rather than audit criteria, and three sentences carry most of it. The first is the one that describes what a maintenance record is for:
Keep records showing that Daily Checks, fault reporting and maintenance work are being carried out as part of day-to-day operations.Heavy Vehicle Accreditation Scheme Operator Guideline 2026, NHVR
The second is the fault loop, and note that it asks for three things rather than one, a log, a check and a ranking:
Ensure reported faults are logged, checked and ranked for repair.Heavy Vehicle Accreditation Scheme Operator Guideline 2026, NHVR
The third sits under the heading Maintenance schedules and methods controls, and it is the one most operators are thinnest on, because a schedule with intervals but no task list only answers half of it:
Have maintenance schedules in place that set out the service intervals and clearly show the work to be done at each service.Heavy Vehicle Accreditation Scheme Operator Guideline 2026, NHVR
The daily check survives the change intact, and the guideline is careful to say what it is not:
The Daily Check focuses on safety-critical components and markers and is not a detailed mechanical inspection.Heavy Vehicle Accreditation Scheme Operator Guideline 2026, NHVR
Read the three requirements together and the day to day paperwork has not changed at all. A daily check with a date and a name on it, a fault raised and ranked, a repair closed out, a service schedule with intervals and tasks. What changed is that nobody will hand you a numbered criterion to tick. You are asked to show the records exist and that the work is happening as part of normal operations, which is a harder thing to fake and an easier thing to satisfy if you were already doing it.
The auditor's designation changed too, and the old phrasing now matches neither scheme:
Your operation will be audited by a HVA scheme approved auditor.Heavy Vehicle Accreditation Scheme Operator Guideline 2026, NHVR
Approved auditors are those registered on the NHVR register of approved auditors.Heavy Vehicle Accreditation Scheme Operator Guideline 2026, NHVR
So if you are writing to somebody about booking an audit, an NHVR auditor and an NHVAS auditor are both the wrong phrase now. The term is a HVA scheme approved auditor, from the NHVR register of approved auditors.
The eight NHVAS standards, as the records they produce
This section is NHVAS only. If you have moved to the HVA scheme there are no numbered maintenance standards to work through and the section above is yours. If you are still on NHVAS, which most accredited operators are, these eight are what the auditor works through. Auditors read them as requirements; it is more useful to read them as the pieces of paper, or rows, that each one expects to exist.
What the daily check covers
The NHVAS standard lists what the daily check inspects, and the HVA guideline describes the same walk around in outcome wording rather than a list. It is short on purpose under both: a look over before it moves, not a service.
- Wheels and tyres, including a visual check of pressure and tread
- Lights and reflectors
- Windows, mirrors and wipers
- Structure and bodywork
- Brakes
- Tow couplings and drawbars
- The accreditation label and the intercept report book
The record has to show when it was done, who did it and how it was recorded, and any fault found goes straight onto the fault report. A tick sheet in the cab with no name and no date meets none of that.
Faults, deferrals and repairs
Under both schemes a driver has to be able to record a fault when it happens and report it to whoever does the maintenance as soon as reasonably practicable, for the trailer as well as the prime mover. On the workshop side, each fault is assessed and given a priority. The HVA guideline compresses that into one sentence, which is worth holding on to as a test of your own system: reported faults are logged, checked and ranked for repair. Two details catch people out. If a fault is deferred or put on watch instead of fixed, the record must name the person who made that call. And when the repair is done, the record shows the fault was rectified and tested, not just closed.
The NHVAS quarterly compliance report
This one is NHVAS only. We searched the 2026 HVA guideline for a quarterly compliance statement and could not find one, so if you have moved across, do not go looking for this obligation in the new scheme. Under NHVAS, once a quarter you write a report on how the module went, and the Maintenance Management Accreditation Guide sets out what goes in it:
Every quarter, you must write a compliance report that lists: the number of nominated vehicles in your fleet; the number of daily checks on nominated vehicles and the number of daily checks that were missed. Daily checks are counted on a per vehicle basis, not vehicle combination basis (e.g. for a B-double combination, this comprises three daily checks); the number of services completed and the number of services that were missed; the total number of fault repairs and total incidences when faults were not rectified; the number of notices issued for a vehicle not complying with vehicle standards regulations.NHVAS Maintenance Management Accreditation Guide, June 2021, NHVR
The line about counting each unit separately is the detail that catches people out, and it is the reason a count taken per combination will not reconcile.
- 1Nominated vehicles
- 2Daily checks undertaken, and the number missed, counted per unit and not per combination
- 3Services completed, and the number missed
- 4Fault repairs, and the times a fault was not rectified
- 5Notices issued for a vehicle not complying with vehicle standards regulations
Most of those are counts of things that were done, and any system that records the doing can produce them. The awkward one is daily checks missed, because to count a miss you have to know which assets worked on which days. Be wary of any software that prints that number without knowing that. A guess on a signed report is worse than a blank.
How long to keep it
Under NHVAS, three years, and the citation for it is narrower than most pages claim. The rule is in the NHVAS Maintenance Management Accreditation Guide of June 2021, under the heading Documents you must keep:
All documents must be kept for a minimum of three years for audit purposes.NHVAS Maintenance Management Accreditation Guide, June 2021, NHVR
It is not in Standard 5, and Standard 5 sets no retention period at all. That is the attribution you will see repeated everywhere, and it is wrong. Maintenance Management Standard 5 in the NHVAS Business Rules and Standards is headed Records and documentation, and its statement is about sufficiency of evidence rather than a period of time:
Documented evidence must be maintained to demonstrate the effective operation of the Maintenance Management System in accordance with the Maintenance Management Standards.NHVAS Business Rules and Standards, Maintenance Management Standard 5, NHVR
We read Standard 5 through, statement and criteria, looking for a period in years, and could not find one. Its criteria are about what must exist: a documented procedure and a register for the nominated vehicles, documentary evidence that the daily check is being done, that faults on the road are recorded and reported, that reported faults are repaired within the nominated deferred time frames, that vehicles are maintained to the set periodic service schedules, and a register of everyone holding a responsibility under the accreditation. A requirement that records exist is not a requirement that they be kept for a set time, and the two get run together constantly.
There is a second three year rule inside NHVAS and it is narrower than it sounds. It sits at Standard 7, Internal review, clause (8), and it is a document control rule about superseded versions of your own procedures rather than about maintenance records. The Accreditation Guide states the same rule in plainer words:
You must keep a record of any changes to documents and procedures. The original documents and procedures must be kept for a minimum of three years.NHVAS Maintenance Management Accreditation Guide, June 2021, NHVR
So if you rewrite your daily check procedure, you keep the old one. That is a different obligation from keeping the checks themselves, and it is the one most systems quietly fail, because procedures get overwritten in place.
The 2026 HVA guideline sets no retention period in years at all. It replaces the number with a proportionality test:
Keep records in a format and for a length of time that allow for audit and review, without creating more administrative tasks than needed for the risk profile of the business.Heavy Vehicle Accreditation Scheme Operator Guideline 2026, NHVR
We searched that guideline for a retention period expressed in years and could not find one. The only figure in years we did find in it concerns a compliance history declaration at application, which is a different thing from how long you hold your maintenance records. That second clause about the risk profile of the business is worth reading twice if you run ten assets rather than two hundred.
Outside accreditation the law names no period that we could find. Three years remains a sensible floor either way, because it is the number NHVAS audits worked to and because an HVA auditor still has to be able to review something. But it is the NHVAS answer rather than a timeless one, and an operator moving across should be working from their own scheme's words and not from a number they remember. The seven year figure you may meet appears in none of the NHVAS Business Rules and Standards, the Maintenance Management Accreditation Guide or the NHVAS Audit Framework.
What an auditor will ask to see
Put plainly, and in roughly the order they ask: the daily checks for an asset they pick, with dates and names. The faults raised from those checks and from the road, and what happened to each one. Any deferral, and who signed it. The repair records, closed out. The service schedule for that asset, with intervals and tasks, and the evidence each service happened when it was due. Who is responsible for what, written down. On NHVAS, the last quarterly compliance report. And then the same again for an asset you did not expect.
That list is the same under both schemes, which is the quietly reassuring part of this page. The HVA wording asks you to keep records showing the work is being carried out as part of day to day operations, and the evidence that satisfies it is the evidence NHVAS asked for. If your records are in order today, the transition is an administrative job rather than a rebuild.
Where a spreadsheet stops being enough
A spreadsheet holds a service schedule well. It does not hold a daily check done by a driver at six in the morning, a fault reported from the road with a photo, or the name of the person who deferred a repair, and it cannot count the quarter for you. Most operators who fail a maintenance audit have done the maintenance. What they cannot do is show it.
Every prestart is filed with the date, the person and photos on the items that failed. Every fault is a record with who raised it and when, and it stays open until a jobcard closes it, showing what was done, by whom, and what it cost, or somebody dismisses it as a duplicate or as needing no work. Service schedules run on kilometres, hours or days and turn red when they slip. Tests proved by a certificate, like a hose pressure test, keep every certificate against the asset. Crew licences, medicals and tickets carry their own expiry. And the compliance statement for any period counts prestarts filed, faults raised, unresolved and resolved, jobcards completed, services overdue and tests done and overdue, exactly, and says on its own face that it does not estimate daily checks missed.
It is $7 an asset a month, $35 minimum, ex GST. One rate for every asset, unlimited users and no contract. The Assistant, which reads a photographed paper jobcard and files it against the asset, is an optional extra at $2 an asset a month. Send us the asset list you already have and we will build it and hand it back loaded, or open an account and paste your rows in yourself. Either way it is thirty days free and we do not take a card to start.
Questions people ask
Sources
Every quotation above was read off these documents on 28 September 2026, and each one was checked from at least two directions before it went up. Two of the links, the NHVR's transition pages, are here for you rather than as citations: we could not read their contents, so nothing on this page is quoted from them. If the NHVR changes any of these, this page is wrong until it is checked again, and the date at the top will tell you.
- Heavy Vehicle Accreditation Scheme Operator Guideline 2026 (NHVR)
- NHVAS Maintenance Management Accreditation Guide, June 2021 (NHVR)
- NHVAS Business Rules and Standards, June 2021 (NHVR)
- HVNL implementation FAQs (NHVR)
- NHVAS transition to HVA scheme (NHVR)
- NHVAS Audit Framework and Auditor Code of Conduct, February 2021 (NHVR)
- Creating heavy vehicle daily checks (NHVR)
- Regulatory advice: the primary duty (NHVR)
- Regulatory advice: maintenance of heavy vehicles used in agricultural or seasonal work (NHVR)
- HVNL implementation: accreditation and safety management systems (NHVR, May 2026)
- Joint release: statutory instruments ahead of the 1 August 2026 commencement (NHVR and NTC, 29 May 2026)
Whichever scheme you are on, the evidence is the same and it has to exist before the auditor asks. Send your asset list and we will set it up and hand it back loaded.
Rather do it on a phone? Prestarts are free for up to 3 assets.
This is a guide, not legal advice. If your operation is accredited, your auditor and the NHVR's own guidance material are the final word.